Republic of the Philippines
SUPREME COURT
Manila

SECOND DIVISION

G.R. No. 184295               July 30, 2014

NATIONAL TRANSMISSION CORPORATION, Petitioner,
vs.
ALPHAOMEGA INTEGRATED CORPORATION, Respondent.

D E C I S I O N

PERLAS-BERNABE, J.:

Assailed in this petition for review on certiorari1 are the Decision2 dated April 8, 2008 and the Resolution3 dated August 27, 2008 of the Court of Appeals (CA) in CA-G.R. SP No. 99454 affirming with modification the Final Award4 of the Construction Industry Arbitration Commission (CIAC) Arbitral Tribunal in favor of respondent Alphaomega Integrated Corporation (AIC) by increasing petitioner National· Transmission Corporation's (TRANSCO) liability from Pl 7,495,117.44 to Pl 8,896,673.31.

The Facts

AIC, a duly licensed transmission line contractor, participated in the public biddings conducted by TRANSCO and was awarded six ( 6) government construction projects, namely: (a) Contract .for the Construction & Erection of Batangas Transmission Reinforcement Project Schedule III (BTRP Schedule III Project); (b) Contract for the Construction & Erection of Batangas Transmission Reinforcement Project Schedule I (BTRP Schedule I Project); (c) Contract for the Construction,Erection & Installation of 230 KV and 69 KV S/S Equipment and Various Facilities for Makban Substation under the Batangas Transmission Reinforcement Project (Schedule II) (Makban Substation Project); (d) Contract for the Construction, Erection & Installation of 138 & 69 KV S/S Equipment for Bacolod Substation under the Negros III-Panay III Substation Projects (Schedule II) (Bacolod Substation Project); (e) Contract for the Construction, Erection & Installation of 138 & 69 KV Substation Equipment for the New Bunawan Switching Station Project (Bunawan Substation Project); and (f) Contract for the Construction, Erection & Installation of 138 and 69 KV Substation Equipment for Quiot Substation Project (Quiot Substation Project).5

In the course of the performance ofthe contracts, AIC encountered difficulties and incurred losses allegedly due to TRANSCO’s breach of their contracts, prompting it to surrender the projects to TRANSCO under protest. In accordance with an express stipulation in the contracts that disagreements shall be settled by the parties through arbitration before the CIAC, AIC submitted a request for arbitration before the CIAC on August 28, 2006, and, thereafter, filed an Amended Complaint against TRANSCO alleging that the latter breached the contracts by its failure to: (a) furnish the required Detailed Engineering; (b) arrange a well-established right-of-way to the project areas; (c) secure the necessary permits and clearances from the concerned local government units (LGUs); (d) ensure a continuous supply of construction materials; and (e) carry out AIC’s requests for power shut down. The aforementioned transgressions resultedin protracted delays and contract suspensions for each project,6 as follows:

Contract Original
Contract
Duration
Duration of
Transco-Approved
Suspension and/or
Extensions
Percentage (%)
of Original
Contract
Duration
1) BTRP Schedule III 560 days 711 days 127%
2) BTRP Schedule I 270 days 406 days 170%
3) Makban Substation 365 days 452 days 124%
4) Bacolod Substation 360 days 289 days 80%
5) Bunawan Substation 330 days 130 days 39%
6) Quiot Substation 300 days 131 days

2119 days7
44%

AIC prayed for judgment declaring all six (6) contracts rescinded and ordering TRANSCO to pay, in addition to what had already been paid under the contracts, moral damages, exemplary damages, and attorney’s fees at ₱100,000.00 each, and a total of ₱40,201,467.19 as actual and compensatory damages.8

TRANSCO, for its part, contended that: (a) it had conducted Detailed Engineering prior to the conduct of the bidding; and (b) it had obtained the necessary government permits and endorsements from the affected LGUs. It asserted that AIC was guilty of frontloading– that is,collecting the bulk of the contract price for work accomplished at the early stages of the project and then abandoning the later stagesof the project which has a lower contract price9 –and that it disregarded the workable portions of the projects not affected by the lack of supplies and drawings. TRANSCO further argued that AIC was estopped from asking for standby fees to cover its overhead expenses during project suspensions considering that the delays, such as the unresolved right-of-way issues and non-availability of materials, were factors already covered by the time extensions and suspensions of work allowed under the contracts.10

On April 18, 2007, the CIAC Arbitral Tribunal rendered its Final Award11 in CIAC Case No. 21-2006 ordering the payment of actual and compensatory damages which AIC would not have suffered had it not been for the project delays attributable to TRANSCO. It found ample evidence to support the claim for the increase in subcontract cost in BTRP Schedule I, as well as such items of cost as house and yard rentals, electric bills, water bills, and maintained personnel, but disallowed the claims for communications bills, maintenance costs for idle equipment, finance charges, and materials cost increases.12 According to the Arbitral Tribunal, even if AIC itself made the requests for contract time extensions, this did not bar its claim for damages as a result of project delayssince a contrary ruling would allow TRANSCO to profit from its own negligence and leave AIC to suffer serious material prejudice as a direct consequence of that negligence leaving it without any remedy at law.13 The Arbitral Tribunal upheld AIC’s right to rescind the contracts in accordancewith Resolution No. 018-2004 of the Government Procurement Policy Board (GPPB), which explicitly gives the contractor the right to terminate the contract if the works are completely stopped for a continuous period of at least 60 calendar days, through no fault of its own, due to the failure of the procuring entity to deliver within a reasonable time, supplied materials, right-of-way, or other items that it is obligated to furnish under the terms of the contract, among others.14 The dispositive portion of the Arbitral Tribunal’s Final Award reads:

WHEREFORE, Respondent, National Transmission Corporation [TRANSCO] is hereby ordered to pay Claimant, Alphaomega Integrated Corporation, the following sums:

(a) For BTRP Schedule III - ₱6,423,496.67
(b) For BTRP Schedule I - 5,214,202.30
(c) For Makban Substation - 3,075,870.95
(d) For Bacolod Substation - 1,362,936.77
(e) For Bunawan Substation - 820,481.72
(f) For Quiot Substation - 598, 129.03
TOTAL ₱17,495,117.44

Each Party shall shoulder its own cost of arbitration.

The foregoing amount of ₱17,495,117.44 shall earn interest at the rate of six percent (6%) per annum from the date of promulgation of this Final Award until it becomes final and executory. Thereafter, the Final Award, including accrued interest, shall earn interest at the rate of 12% per annum until the entire amount due is fully paid.15 (Emphasis supplied)

Unconvinced, TRANSCO instituted a petition for review16 with the CA.

Before filing its comment17 to the petition, AIC moved for the issuance of a writ of execution,18 not for the amount of 17,495,117.44 awarded in the Final Award, but for the increased amount of 18,967,318.49.19 It sought correction of the discrepancies between the amount of the award appearing in the dispositive portion20 and the body of the Final Award.21 The Arbitral Tribunal, however, denied AIC’s motion, holding that while the CIAC Revised Rules of Procedure Governing Construction Arbitration (CIAC Rules) would have allowed the correction of the Final Award for evident miscalculation of figures, typographical or arithmetical errors, AIC failed to file its motionfor the purpose within the time limitation of 15 days from its receipt of the Final Award.22

The CA Ruling

In the Decision23 dated April 8, 2008, the CAaffirmed the Arbitral Tribunal’s factual findings that TRANSCOfailed to exercise due diligence in resolving the problems regarding the right-of-way and the lack of materials before undertaking the bidding process and entering into the contracts with AIC.24 It found no merit in TRANSCO’s allegation that AIC refused to perform the remaining workable portions of the projects not affected by problems of right-of-way, shutdowns, supplies and drawings, firstly, because the certificates ofaccomplishments issued by TRANSCO in the course of project implementation signifying its satisfaction with AIC’s performance negate such claim and, secondly, because all the orders issued by TRANSCO suspended the contracts not only in part but in their entirety, thus, permitting no work activity at all during such periods.25

The CA upheld the Arbitral Tribunal’s Final Award as having been sufficiently established by evidence but modified the total amount of the award after noting a supposed mathematical error in the computation. Setting aside TRANSCO’s objections, it ruled that when a case is brought to a superior court on appeal every aspect of the case is thrown open for review,26 hence, the subject error could be rectified. The CA held that the correct amount of the award should be ₱18,896,673.31, and not ₱17,495,117.44 as stated in the Arbitral Tribunal’s Final Award.27 Dissatisfied, TRANSCO moved for reconsideration28 but was, however, denied by the CA in a Resolution29 dated August 27, 2008, hence, the instant petition.

The Issues Before the Court

The essential issues for the Court’s consideration are whether or not the CA erred (a) in affirming the CIAC Arbitral Tribunal’s findings that AIC was entitled to its claims for damages as a result of project delays, and (b) in increasing the total amount of compensation awarded in favor of AIC despite the latter’s failure to raise the allegedly erroneous computation of the award before the CIAC in a timely manner, that is, within fifteen (15) days from receipt of the Final Award as provided under Section 17.1 of the CIAC Rules.

The Court’s Ruling

TRANSCO seeks through this petition a recalibration of the evidencepresented before the CIAC ArbitralTribunal, insisting that AIC is not entitled to any damages not only because it had previously waived all claims for standby fees in case of project delays but had eventually failed to perform the workable portions of the projects. This is evidently a factual question which cannot be the proper subject of the present petition. Section 1, Rule 45 of the Rules of Court provides that a petition for review on certiorariunder the said rule, as in this case, "shall raise only questions of law which must be distinctly set forth." Thus, absent any of the existing exceptions impelling the contrary, the Court is, as a general rule, precluded from delving on factual determinations, as what TRANSCO essentially seeks in this case. Similar to the foregoing is the Court’s ruling in Hanjin Heavy Industries and Construction Co., Ltd. v. Dynamic Planners and Construction Corp.,30 the pertinent portions ofwhich are hereunder quoted:

Dynamic maintains that the issues Hanjin raised in its petitions are factual in nature and are, therefore, not proper subject of review under Section 1 of Rule 45, prescribing that a petition under the said rule, like the one at bench, "shall raise only questions of law which must be distinctly set forth." Dynamic’s contention is valid topoint as, indeed, the matters raised by Hanjin are factual, revolving as they do on the entitlement of Dynamic to the awards granted and computed by the CIAC and the CA. Generally, this would be a question of fact that this Court would not delve upon. Imperial v. Jauciansuggests as much. There, the Court ruled that the computation of outstanding obligation is a question of fact:

Arguing that she had already fully paid the loan x x x, petitioner alleges that the two lower courts misappreciated the facts when they ruled that she still had an outstanding balance of ₱208,430.

This issue involves a question of fact. Such question exists when a doubt or difference arises as to the truth or the falsehood of alleged facts; and when there is need for a calibration of the evidence, considering mainly the credibility of witnesses and the existence and the relevancy of specific surrounding circumstances, their relation to each other and to the whole, and the probabilities of the situation. (G.R. No. 149004, April 14, 2004, 427 SCRA 517, 523-524.)

The rule, however, precluding the Court from delving on the factual determinations of the CA, admits of several exceptions. In Fuentes v. Court of Appeals, we held that the findings of facts of the CA, which are generally deemed conclusive, may admit review by the Court in any of the following instances, among others:

(1) when the factual findings of the [CA] and the trial court are contradictory;

(2) when the findings are grounded entirely on speculation, surmises, or conjectures;

(3) when the inference made bythe [CA] from its findings of fact is manifestly mistaken, absurd, or impossible;

(4) when there is grave abuse of discretion in the appreciation of facts;

(5) when the [CA], in making its findings, goes beyond the issues of the case, and such findings are contrary to the admissions of both appellant and appellee;

(6) when the judgment of the [CA] is premised on a misapprehension of facts;

(7) when the [CA] fails to notice certain relevant facts which, if properly considered, will justify a different conclusion;

(8) when the findings of fact are themselves conflicting;

(9) when the findings of fact are conclusions without citation of the specific evidence on which they are based; and

(10) when the findings of fact of the [CA] are premised on the absence of evidence but such findings are contradicted by the evidence on record. (G.R. No. 109849, February 26, 1997, 268 SCRA 703, 709)

Significantly, jurisprudence teaches that mathematical computations as well as the propriety of the arbitral awards are factual determinations. And just as significant is that the factual findings of the CIAC and CA—in each separate appealed decisions—practically dovetail with each other. The perceptible essential difference, at least insofar as the CIAC’s Final Award and the CA Decision in CA-G.R. SP No. 86641 are concerned, rests merely on mathematical computations or adjustments of baseline amounts which the CIAC may have inadvertently utilized.31 (Emphases and underscoring supplied)

In any case, the Court finds no reason to disturb the factual findings of the CIAC Arbitral Tribunal on the matter of AIC’s entitlement to damages which the CA affirmed as being well supported by evidence and properly referred to in the record. It is well-settled that findings of fact of quasijudicial bodies, which have acquired expertise because their jurisdiction is confined to specific matters, are generally accorded not only respect, but also finality, especially when affirmed by the CA.32 The CIAC possesses that required expertise in the field of construction arbitration and the factual findings of its construction arbitrators are final and conclusive, not reviewable by this Court on appeal.33

While the CA correctly affirmed infull the CIAC Arbitral Tribunal’s factual determinations, it improperly modified the amount of the award in favor of AIC, which modification did not observe the proper procedure for the correction of an evident miscalculation of figures, including typographical or arithmetical errors, in the arbitral award. Section 17.1 of the CIAC Rules mandates the filing of a motion for the foregoing purpose within fifteen (15) days from receipt thereof, viz.:

Section 17.1 Motion for correction of final award– Any of the parties may file a motion for correction of the Final Award within fifteen (15) days from receipt thereof upon any of the following grounds:

a. An evident miscalculation of figures, a typographical or arithmetical error; (Emphasis supplied)

x x x x

Failure to file said motion would consequentlyrender the award final and executory under Section 18. 1 of the same rules, viz.:

Section 18.1 Execution of Award – A final arbitral award shall become executory upon the lapse of fifteen (15) days from receipt thereof by the parties.1âwphi1

AIC admitted that it had ample time to file a motion for correction of the Final Award but claimed to have purposely sat on its right to seek correction supposedly as a strategic move against TRANSCO34 and, instead, filed with the CIAC Arbitral Tribunal on June 13, 2007 a "Motion for Issuance of Writ of Execution for the Total Amount of 18,967,318.49 as Embodied in the Final Award."35 The Arbitral Tribunal eventually denied AIC’s aforesaid motion for execution because, despite its merit, the Arbitral Tribunal could not disregard the time-limitation under the CIAC Rules.36 Clearly, having failed to move for the correction of the Final Award and, thereafter, having opted to file insteada motion for execution of the arbitral tribunal’s unopposed and uncorrected Final Award, AIC cannot now question against the correctness of the CIAC’s disposition. Notably, while there is jurisprudential authority stating that "[a] clerical error in the judgment appealed from may be corrected by the appellate court,"37 the application of that rule cannot be made in this case considering that the CIAC Rules provides for a specific procedureto deal with particular errors involving "[a]n evident miscalculation of figures, a typographical or arithmetical error." Indeed, the rule iswell entrenched: Specialis derogat generali. When two rules apply to a particular case, thatwhich was specially designed for the said case must prevail over the other.38

Furthermore, it must be emphasized that the petition for review before the CA was filed by TRANSCO.39 AIC never elevated before the courts the matter concerning the discrepancy between the amount of the award stated in the body of the Final Award and the total award shown in its dispositive portion. The issue was touched upon bythe CA only after AIC raised the same through its Comment (With Motion to Acknowledge Actual Amount of Award)40 to TRANSCO’s petition for review. The CA should not have modified the amount of the award to favor AIC because it is well-settled that no relief can be granted a party who does not appeal41 and that a party who did not appeal the decision may not obtain any affirmative relief from the appellate court other than what he had obtained from the lower court, if any, whose decision is brought up on appeal.42 The disposition, as stated in the fallo of the CIAC Arbitral Tribunal's Final Award, should therefore stand.43

WHEREFORE, the petition is PARTLY GRANTED. The Decision dated April 8, 2008 of the Court of Appeals in CA-G.R. SP No. 99454 is hereby AFFIRMED with MODIFICATION. The compensation awarded in favor of Alphaomega Integrated Corporation in the amount of ₱17,495,117.44, as shown in the fallo of the ·construction Industry Arbitration Commission's Final Award dated April 18, 2007, stands.

SO ORDERED.

ESTELA M. PERLAS-BERNABE
Associate Justice

WE CONCUR:

ANTONIO T. CARPIO
Associate Justice
Chairperson

ARTURO D. BRION
Associate Justice
JOSE PORTUGAL PEREZ
Associate Justice

BIENVENIDO L. REYES*
Associate Justice

A T T E S T A T I O N

I attest that the conclusions in the above Decision had been reached in consultation before the case was assigned to the writer of the opinion of the Court's Division.

ANTONIO T. CARPIO
Associate Justice
Chairperson, Second Division

C E R T I F I C A T I O N

Pursuant to Section 13, Article VIII of the Constitution, and the Division Chairperson's Attestation, I certify that the conclusions in the above Decision had been reached in consultation before the case was assigned to the writer of the ppinion of the Court's Division.

MARIA LOURDES P. A. SERENO
Chief Justice


Footnotes

* Designated Additional Member in lieu of Justice Mariano C. Del Castillo, per Raffle dated July 23, 2014.

1 Rollo, pp. 10-82.

2 Id. at 84-121. Penned by Asso"ciate Justice Arcangel,ita M. Romilla-Lontok, with Associate Justices Mariano C. Del Castillo (now Member of the Court) and Ricardo R. Rosario, concurring.

3 Id. at 123-124.

4 Id. at 164-248.

5 Id. at 85-86.

6 See id. at 87-89.

7 Id. at 87.

8 Id. at 95-96.

9 Id. at 98.

10 Id.

11 Id. at 164-248.

12 Id. at 244-246.

13 Id. at 229.

14 Id. at 227.

15 Id. at 248.

16 Id. at 252-312. Dated June 12, 2007.

17 Id. at 313-343. Comment (With Motion to Acknowledge Actual Amount of Award) Dated August 24, 2007.

18 Id. at 344-349. Motion for Issuance of Writ of Execution for the Total Amount of 18,967,318.49 as Embodied in the Final Award dated June 13, 2007.

19 Id. at 349.

20 Id. at 248.

21 Id. at 245-246.

22 Id. at 350-352. Order dated June 18, 2007 issued by Chairman Custodio O. Parlade.

23 Id. at 84-121.

24 Id. at 112-113.

25 Id. at 117-118.

26 Id. at 119.

27 Id. at 119-120.

28 See Motion for Reconsideration dated April 29, 2008; id. at 125-155

29 Id. at 123-124.

30 576 Phil. 502 (2008).

31 Id. at 519-520.

32 Public Estates Authority v. Uy, 423 Phil. 407, 416 (2001).

33 Shinryo (Philippines) Company, Inc. v. RRN Incorporated, G.R. No. 172525, October 20, 2010, 634 SCRA 123, 130, citing IBEX International, Inc. v. Government Service Insurance System, 618 Phil. 306, 312 (2009).

34 See Rollo, p. 348.

35 Id. at 344-349.

36 Id. at 250.

37 Soler v. Bastida, G.R. No. L-22822, March 19, 1925. See also National Bank v. De la Viña (46 Phil. 63 [1924]).

38 Office of the Ombudsman v. Chavez, G.R. No. 172206, July 3, 2013, 700 SCRA 409-410.

39 Rollo, pp. 252-312.

40 Id. at 318-343.

41 Pascual v. Ramos, G.R. No. 144712, July 4, 2002, 384 SCRA 105, 116.

42 Daabay v. Coca-cola Bottlers Phils., Inc., G.R. No. 199890, August 19, 2013, 384 SCRA 105, 116.

43 "The resolution of the court in a given issue embodied in the fallo or dispositive part of a decision or order is the controlling factor as to settlement of rights of'the parties. Thus, where there is a conflict between the falfo· and the ratio decidendi or body of the decision, the fallo controls. This rule rests on the theory that the fallo is the final order while the opinion in the body is merely a statement ordering nothing. The rule applies when the dispositive part of a final decision or order is definite, clear, and unequivocal, and can wholly be given effect without need of interpretation or construction." (Obra v. Spouses Badua, 556 Phil. 456, 461 [2007]; citations omitted.)


The Lawphil Project - Arellano Law Foundation